Construction quantity take-off
Measure the floor finishes for three rooms from a fictional revision B drawing. Quantities are measured in square metres, with waste applied separately.
Reception
5 m × 4 mMeeting room
3 m × 4 mWorkroom
6 m × 4 m
5 m × 4 mMeeting room
3 m × 4 mWorkroom
6 m × 4 m
| Room | Drawing reference | Net area | Order quantity |
|---|---|---|---|
| Reception | A-101 · grid A1 | 20.00 m² | 22.00 m² |
| Meeting room | A-101 · grid A2 | 12.00 m² | 13.20 m² |
| Workroom | A-101 · grid B1 | 24.00 m² | 26.40 m² |
| Total | 10% allowance | 56.00 m² | 61.60 m² |
Acceptance check
Check one room against the drawing and confirm the 10% waste allowance. Confirm the finish boundary at thresholds before ordering.
Review and sign-off
Estimator prepares the take-off. A second reviewer checks drawing revision, units and quantities. The buyer approves allowances and exclusions.