Construction quantity take-off

Measure the floor finishes for three rooms from a fictional revision B drawing. Quantities are measured in square metres, with waste applied separately.

Drawing A-101 · Revision B · Schematic plan, not to scale.
RoomDrawing referenceNet areaOrder quantity
ReceptionA-101 · grid A120.00 m²22.00 m²
Meeting roomA-101 · grid A212.00 m²13.20 m²
WorkroomA-101 · grid B124.00 m²26.40 m²
Total10% allowance56.00 m²61.60 m²

Acceptance check

Check one room against the drawing and confirm the 10% waste allowance. Confirm the finish boundary at thresholds before ordering.

Review and sign-off

Estimator prepares the take-off. A second reviewer checks drawing revision, units and quantities. The buyer approves allowances and exclusions.